Reducing Rebuild Lead Time for Drilling Equipment to Expedite Return to Drilling Sites
Industry: Oilfield Services
Duration: 4 months
Locations: Midland & Conroe, TX
Value Created: Lead times down from weeks to days
Situation
Drilling equipment rebuild lead times were unpredictable and excessively long, limiting tool availability and slowing field operations. Logistics were inconsistent, rework was common, and teams lacked visibility into flow performance.
Approach
Conducted full value‑stream mapping across both sites
Implemented TPM in Midland to reduce downtime
Redesigned Conroe’s shop layout for optimized flow
Streamlined logistics and replenishment
Introduced daily tier meetings and KPI hierarchy
Coached practitioners to sustain improvements independently
Results
85% reduction in total relining lead time
Increased tool availability and field responsiveness
Lower rework rates and clearer root‑cause tracking
Improved decision cycles through visible metrics